At Least 11 Education Ministry Contracts Terminated Due to Contractor Failures

The Guyana Times reports that at least 11 contracts under the Education Ministry were terminated this year because contractors failed to complete the agreed-upon work. The Attorney General’s Chambers and Legal Affairs Ministry confirmed these terminations after review by its Contract Review Unit, and the government stated it intends to pursue legal action against contractors where necessary.

A conceptual illustration of an empty, partially constructed building frame under dramatic lighting, symbolizing terminated education ministry contracts.
AI-generated illustration

The Guyana Times reported that a minimum of 11 contracts awarded under the Education Ministry were terminated during the current year because the contractors did not execute the agreed-upon works. This information was disclosed on Wednesday by the Attorney General’s Chambers and Legal Affairs Ministry, which confirmed the terminations following an examination by its Contract Review Unit.

K’s Trucking and Construction had its contracts for the construction of a students’ dormitory, multipurpose hall, and kitchen at Monkey Mountain, Region Eight (Potaro-Siparuni), Lots 1 and 2, terminated on June 29, 2026. The reason cited for this termination was the contractor's failure to execute the works and having insufficient financial, technical, and human resource capacity.

Rahaman Construction and Transportation Services' contract for building a female dormitory at the Kwakwani Secondary School in Region 10 (Upper Demerara-Bebrice) was terminated on March 10, 2026. This followed the contractor's failure to begin and execute the works, failure to mobilize adequate resources, and consistent noncompliance with contractual obligations.

Modular Construction Services' contract for the design and build of the reconstruction of the Kwakwani Secondary School was terminated on July 8, 2026, due to the failure to commence and execute the works.

Furthermore, the contract for Lot 2 of the Dora Secondary School extension in Kuru Kuru, Linden Highway, awarded to 4S Security and Building Enterprise, was terminated on March 10, 2026. This was attributed to the company's failure to mobilize sufficient resources, its lack of response to official correspondence, and its failure to take corrective action.

A contract for the construction of the Karasabai Secondary School in Region Nine (Upper Takutu-Upper Essequibo), awarded to Avinash Contracting and Scrap Metal Inc, was terminated on October 30, 2026, because the firm failed to execute the works according to the approved program and experienced delays exceeding the contractual limit.

D&S Construction was removed from the project to construct Vreed-en-Hoop Secondary School Lot 2, Blocs 2 and 3, on October 27, 2026, due to poor progress and inadequate resources.

Other terminated contracts included one for LS Contracting Services to extend a staffroom at Stewartville Secondary School, and one for Jemcorp Engineering and Imports for the construction and furnishing of home economics and industrial technology labs at St Cuthberts Mission. A contract awarded to Rawl Davis Contracting Services for the rehabilitation of the Wiruni Nursery School was also terminated, though no reasons were provided for that termination.

Sheriff Construction Inc's contract for building a students’ dormitory at Jawalla, Region Seven (Cuyuni-Mazaruni), was terminated on November 5, 2026. The Ministry stated that the $310 million contract was awarded on October 16, 2024, with work starting in December 2024 and an expected completion date of October 2025. However, despite the contractor requesting an extension until February 2026, the project was only at six per cent progress, which the Ministry noted indicated significant delays in execution.

Regarding the Jawalla dorm project, the Ministry noted that payments included a mobilization advance of $46 million and an Interim Payment Certificate (IPC) payment of $7 million, from which $3.6 million had been deducted.

Blueprint Builders Inc.'s contract for the construction of Lot 2 of the multipurpose hall and kitchen at Kopinnang, North Pakaraimas, was terminated on November 5, 2026, for similar reasons. The Ministry stated that the $149 million contract was awarded on March 1, 2025, with a deadline of November 1, 2026; however, after about seven months, the project was only six per cent complete.

Concerning the Kopinnang project, the Ministry mentioned that an advance payment of $52 million was made, with Assuria providing mobilization security on February 28, 2026, and performance security on August 26, 2026. The Ministry observed that after roughly seven and a half months, only six per cent of the work was finished, pointing to significant delays in project execution, and recommended the contract's termination due to the unsatisfactory progress.

During his appearance on the program “Issues in the News” on Tuesday, Attorney General Anil Nandlall stated that in addition to the contract terminations, the Government would initiate legal action against contractors when necessary. Nandlall indicated that the required legal steps would be taken, and legal proceedings would be filed if the Review Team members deemed it appropriate, with the proceedings seeking necessary compensatory remedies. He specified that they would claim damages for breach of contract, losses of various types, and would seek to recover liquidated damages and other punitive sanctions as provided in the contracts.